Implementation roadmap
From first conversation to go-live, phase by phase.
Implementation is an 8-phase methodology — discovery, solution design, configuration, data migration, testing, training, launch, and post-launch — that maps your real processes to the product before go-live, not a generic onboarding checklist run the same way for every customer.
Small teams often run these phases themselves in the free trial. Larger rollouts can have our help, quoted for the scope. How long each phase takes depends on the business, the number of apps and the state of the data, so no fixed timeline is given here.
Phase 1
Discovery
Before any configuration happens, discovery maps your real processes — not a generic template. This is where a manufacturer's actual BOM complexity, a distributor's warehouse count, or a services firm's billing models get understood directly, matching the evaluation criteria a real buying committee actually checks.
- · Document current systems and where data actually lives today (spreadsheets, Tally/QuickBooks/Zoho, a legacy or point tool)
- · Map real business processes module by module — which of the 12 modules apply, and which capability groups within them matter most
- · Identify the specific workflows that matter most (e.g. plan-to-production, procure-to-pay, hire-to-payroll)
- · Surface honest scope questions early — what the product does and does not do today, referenced against real capability groups, not assumed
Phase 2
Solution Design
What we learn becomes a clear design: which apps, which workflows, and how departments, roles and document numbering map to your business.
- · Set up departments, teams, warehouses and locations, and decide who sees which records
- · Decide roles and access: which ready-made roles fit, and where access should be limited or time-bound
- · Plan approval thresholds and governance rules (quotation approval limits, journal approval thresholds, matching tolerances) against real policy, not defaults left unexamined
- · Confirm the numbering-series scheme for invoices, purchase orders, and other documents
Phase 3
Configuration
Sign-up already creates the ready-made roles and document numbering, so setup starts from there and adapts it to your design rather than starting from nothing or leaving the defaults.
- · Set up departments, teams and warehouses as designed
- · Adjust roles, permission packages, and any custom roles the design called for
- · Set approval thresholds, matching tolerances, and other governance rules module by module
- · Configure the chart of accounts, tax rules, and localisation settings (India-default: en-IN, Asia/Kolkata, INR, April-start fiscal year, adjustable per organisation)
Phase 4
Data Migration
Customers, items, suppliers, and open transactions are migrated and reconciled as part of implementation — a real service commitment, not an automated one-click import. This phase gets the expanded treatment because it's the step most implementation-risk objections are really about.
- · Extract master data from current systems — items, parties (customers/suppliers), addresses, unit-of-measure, bills of material
- · Cleanse and deduplicate before import — a spreadsheet's drift (duplicate customers, inconsistent item codes) doesn't get carried into the new system as-is
- · Migrate open transactions (open sales orders, open purchase orders, outstanding invoices/bills) so operations don't have a gap at go-live
- · Reconcile migrated data against source-system totals before sign-off — balances, quantities, and outstanding amounts are checked, not assumed correct
Phase 5
Testing
Configured workflows are validated against real scenarios drawn from discovery — not a generic test script — before anyone depends on the system for a live transaction.
- · Run real workflow scenarios end to end (e.g. a real quotation through to invoice, a real purchase order through to matched vendor bill)
- · Validate approval routing and self-approval blocking behave as designed
- · User acceptance testing with the actual people who will use the system day to day, not just IT
Phase 6
Training
Role-based training matches the real role and permission design from solution design — a warehouse clerk isn't trained on the same screens as a finance controller.
- · Role-based training sessions matching each real permission package
- · Hands-on practice in a real, isolated workspace before go-live
- · Documentation and reference material specific to the configured workflows, not generic product documentation
Phase 7
Launch
Go-live starts your subscription and switches on the agreed apps for your team.
- · Final reconciliation check on migrated data
- · Subscription started and apps switched on
- · Go-live cutover, with the prior system typically kept read-only for a reconciliation window rather than switched off immediately
Phase 8
Post-Launch
Early usage surfaces configuration refinements discovery couldn't fully anticipate — approval thresholds that turn out too tight or too loose, a report a team actually needs that wasn't scoped, a role that needs narrower access than first designed.
- · Hypercare support during the initial usage period
- · Configuration refinement based on real usage patterns
- · Adoption review against the reporting and dashboards each role actually uses
Moving data across? See data migration.